And, while we were away, the workmen did play!

Wow! While we were away, they framed the inside and put the tubs in. They marked where the appliances would be, finished the basement floor, and put in windows and doors!!! And, we also have HVAC in there already! All of this done in one week! So much so fast... and we can't wait to move in.









And, while we were away, we also locked in the interest rate... 4.25%. We are thrilled! These record breaking rates are amazing! I guess there is something with a credit from NVR... that is not incorporated into the 4.25%. Regardless, our annual percentage rate will be 4.95%... we can definitely live with that - it's nearly .2% lower than our original good faith estimate and will save a whole lot of money in interest over the course of the loan (something like $14k) and in the closing costs.
We got a call from the electrician that they are a few days ahead of schedule and they will be in there tomorrow (Monday) to begin wiring.
There is even more... we have our closing date... our pre-settlement meeting is Friday, October 22 and our Settlement meeting is Tuesday, October 26... Everything is happening so quick. Good thing we started packing a while ago!







No comments:

Post a Comment